SIG/HPC meeting 2023-07-27¶
Attendees:¶
* Sherif
* Jeremy Siadal
* Stack
* Scott Groel
* Gregory Kurtzer
Discussions:¶
Chris, talked about the slurm system unit bug in upstream
Sherif, asked about the openQA status
Stack, they are working on that and still improving it
Sherif, asked about the PMIX support and how to do it
Jeremy, it is a bit more complex than what it seems but worth doing
David, what is the added value from moving the PMIX to newer version
Jeremy, we need to look at the user base and see if this is needed
Stack, asks about PMIX and what it is
David, the extension for pmix is more needed when you implement on scale and performance is an issue within slurm
Greg, we can have pmix into the SIG, that's not a bad idea
Jeremy, we will also need runtime aspects of it
David, yes we will need both
Jeremy, mentioned a package they would like to have into SIG/HPC they will send it to us
Greg, will reach out to openPBS and cloud charly
Action items:¶
* Sherif: Reach out to jose-d about pmix - Done, no feedback yet -
* Greg: to reach out to openPBS and clout charly
* Sherif: To update slurm32 to latest
Old business:¶
2023-07-13:¶
* Sherif needs to update the wiki - Done
* Sherif to look into MPI stack
* Chris will send Sherif a link with intro
2023-06-29:¶
* Sherif release slurm23 sources - Done
* Stack and Sherif working on the HPC list
* Sherif email Jeremy, the slurm23 source URL - Done
2023-06-15:¶
* Sherif to look int openHPC slurm spec file - Pending on Sherif
* We need to get lists of centres and HPC that are moving to Rocky to make a blog post and PR
2023-06-01:¶
* Get a list of packages from Jeremy to pick up from openHPC - Done
* Greg / Sherif talk in Rocky / RESF about generic SIG for common packages such as chaintools
* Plan the openHPC demo Chris / Sherif - Done
* Finlise the slurm package with naming / configuration - Done
2023-05-18:¶
* Get a demo / technical talk after 4 weeks "Sherif can arrange that with Chris" - Done
* Getting a list of packages that openHPC would like to move to distros "Jeremy will be point of contact if we need those in couple of weeks" - Done
2023-05-04¶
* Start building slurm - On going, a bit slowing down with R9.2 and R8.8 releases, however packages are built, some minor configurations needs to be fixed -
* Start building apptainer - on hold -
* Start building singulartiry - on hold -
* Start building warewulf - on hold -
* Sherif: check about forums - done, we can have our own section if we want, can be discussed over the chat -
2023-04-20¶
* Reach out to other communities “Greg” - on going -
* Reaching out for different sites that uses Rocky for HPC “Stack will ping few of them and others as well -Group effort-”
* Reaching out to hardware vendors - nothing done yet -
* Statistic / public registry for sites / HPC to add themselves if they want - nothing done yet -